Today was a milestone day, we had rough inspection on plumbing, electrical, and framing. Each only made a few comments, nothing significant. The wanted the plans changed to show the placement of the furnace. They wanted to remind the carpenter of the stair length and wanted the fireblock caulk in place before the inspection. I guess the contractor is used to an insulation inspection and the caulk is usually part of that. Now the inspector has to return to look at caulk, go figure.

I did a lot of little projects. Added a few studs for mounting the TV's later. Helped configure the "old" attic access area. Put in some insulation along the outside walls under the floor as long as it was up. And of course did more staining/finishing of the trim in the garage. Getting close to being done with the trim, at least what they have brought me.